    The rehabilitation of Beira' Storm Water Drainage Systems was developed in 2 phases:

    • Feasibility study for storm water drainage in the center and north of the city and the engineering projects for the central and southern regions and
    • Supervision of the rehabilitation works.

    The work included the following activities:

    • Review and critical analysis of the adequacy of the technical solutions presented in the Feasibility Study and Final Design;
    • Preparation of technical support documentation for the tender process;
    • Preparation of the Environmental Impact Assessment (EIA), Environmental Management Plan (EMP) and Population Resettlement Action Plan;
    • Supervision of the construction / rehabilitation of Beira drainage system, which is the main channel known as "central", consisting of channels A, AII and AIV, for a total of 9.3 km, including project analysis and review, testing and commissioning.
  • Assignment
  • Assignment
    • Feasibility Studies
    • Final Design
    • Environmental Impact Assessment
    • Resettlement Plan
    • Construction Supervision
  • general data
  • Work’s Value
    1,3 Million €
  • Dates
    from 2013
  • Site
    Beira
  • Country
    Mozambique
  • Client
    AIAS - ADMINISTRAÇÃO DE INFRAESTRUTURAS DE ÁGUA E SANEAMENTO
  • Companies
    TPF Consultores, TPF Moçambique